Record — Re: WMS - Financial Package (Page 1691)
A. Michael Carroll III, MCPPO
Colliers Project Leaders
mike.carroll@collierseng.com
Direct: 857 557 5799 | Cell: 781 844 0098 | Main: 877 627 3772
cplusa.com
DISCLAIMER This e-mail is confidential. It may also be legally privileged. If you are not the addressee you
may not copy, forward, disclose or use any part of this email text or attachments. If you have received this
message in error, please delete it and all copies from your system and notify the sender immediately by
return e-mail. Internet communications cannot be guaranteed to be timely, secure, error or virus free. The
sender does not accept liability for any errors or omissions. Any drawings, sketches, images, or data are to
be understood as copyright protected.
From: Ottina.Kathleen <KOttina@whitman-ma.gov>
Sent: Sunday, July 21, 2024 7:40 PM
To: Shirley Ng <shirley.ng@collierseng.com>; Mike Carroll <mike.carroll@collierseng.com>
Cc: Jeffrey Szymaniak <jeffrey.szymaniak@whrsd.org>
Subject: Re: WMS - Financial Package
This Message originated outside your organization.
■■Hi Shirley and Mike,
Thank you for sending me this seven-page document. It contains exactly the information I was
looking for.
I have a concern that the information on page 4 "Expenditures - Invoices/Requisitions" shows that
the total spent to date is $6,380,629.18. But when I look at the information on page 5 - "Estimated
Project Cash Flow Sheet" the total actual cumulative through June 24 is $4,831,052. That's a $1.5
million difference. Am I trying to compare two pieces of information that are not truly comparable?
Bottom line is I would like to know how much we have actually spent. I've never served on a building
committee with a $135 million budget and I need to get a handle on the financial information while it's
still relatively easy to follow; two vendors Colliers and Ai3. Once we start getting Invoices for the
actual construction phase I need to have already developed my approach to staying on top of the
finances.
I look forward to receiving some advice/information from you tomorrow on this topic. As the Whitman
Finance Committee Chair it is my sincere hope that the FY25 tax rate will be set without any
additional borrowing for the Middle School Project. I'm using the Estimated Project Cash Flow Sheet
to predict when we will need to go out for additional borrowing. I really hope it is some time after
January 2025, so that any payments will be due in FY26.
See you tomorrow at 9:00.
Kathleen