2024-04-29 — Re: MSBA/Whitman-Hanson RSD: Whitman Middle School, DD Submission Review Comments
From: "Jeffrey Szymaniak <jeffrey.szymaniak@whrsd.org>" <jeffrey.szymaniak@whrsd.org>
To: Mike
Cc: George; Julie; Troy
Bcc: george.ferro@whrsd.org
Date: 2024-04-29 12:01
Subject: Re: MSBA/Whitman-Hanson RSD: Whitman Middle School, DD Submission Review Comments
Ok
Jeff Szymaniak
Superintendent
Whitman-Hanson RSD
@WH_Super
Semper Ad Maiora
On Mon, Apr 29, 2024 at 11:59 AM Mike Carroll <mike.carroll@collierseng.com> wrote:
Jeff,
We had you sign it, but there were some issues with the dates and titles, etc.. Please see the attached email sent to
Jennifer last week.
I talked to her on Friday and we planned to get these all signed up tomorrow evening at the SBC meeting.
Thanks,
Mike
A Michael Carroll III, MCPPO
Colliers Project Leaders
mike.carroll@collierseng.com
Mobile: 781 844-0098
cplusa.com
From: Jeffrey Szymaniak <jeffrey.szymaniak@whrsd.org>
Sent: Monday, April 29, 2024 11:51 AM
To: Mike Carroll <mike.carroll@collierseng.com>; Troy Randall <randall@ai3architects.com>; George Ferro
<george.ferro@whrsd.org>; Julie Rivera <rivera@ai3architects.com>
Subject: Fwd: MSBA/Whitman-Hanson RSD: Whitman Middle School, DD Submission Review Comments
This Message originated outside your organization.
Hi folks,
Did we miss something? Were we supposed to submit a PFA? I'm sure this is going to come up tomorrow.
Jeff