2024-03-28 — RE: MSBA/Whitman-Hanson Regional School District – Whitman Middle School Project, Scope and Budget
From: "Mike Carroll <mike.carroll@collierseng.com>" <mike.carroll@collierseng.com>
To: Jennifer; Szymaniak.Jeffrey
Cc: beth.stafford@whrsd.org; Mike; Brian; Anne; Julie; Matt; Christina; Katie; Troy; mcarter@whitman-ma
.gov; CKowalski@whitman-ma.gov; Harani; Stanbrook.John; "jennifer.kroese@whrsd.org" <Jennifer>
; August
Bcc: beth.stafford@whrsd.org
Date: 2024-03-28 13:20
Subject: RE: MSBA/Whitman-Hanson Regional School District – Whitman Middle School Project, Scope and Budget
Agreement
Attachments: image001.png
Good afternoon Jennifer,
I just wanted to provide an update on the signing of the PSBA. This was presented at the SBC on Tuesday 03/26/24 and
approved.
The district is now in the process of executing all of the documents and we should have a package out by the end of next
week at the latest.
I know that it requests that the documents be mailed, but we will also be scanning for us to save, so I will probably send you
them electronically as well as the hard copy.
Please note on the last item required, the certified vote. We can provide a draft of the 03/26/24 meet minutes next week, but
we will need to follow up with the certified copy after they are voted on. We current are scheduled for the next SBC to be on
04/30/24, we can have the minutes approved that night and then certified and sent to you after that.
Should you have any questions, please let us know.
Thanks,
Mike
A Michael Carroll III, MCPPO
Colliers Project Leaders
Boston, MA
mike.carroll@collierseng.com
Mobile: 781 844-0098
cplusa.com
From: Jennifer Flynn <Jennifer.Flynn@massschoolbuildings.org>
Sent: Thursday, March 7, 2024 3:26 PM
To: Szymaniak.Jeffrey <Jeffrey.Szymaniak@whrsd.k12.ma.us>
Cc: Anne Hudson <Anne.Hudson@MassSchoolBuildings.org>; August Knuth <August.Knuth@MassSchoolBuildings.org>; Brian Kelley
<Brian.Kelley@MassSchoolBuildings.org>; CKowalski@whitman-ma.gov; mcarter@whitman-ma.gov; beth.stafford@whrsd.org; Stanbrook.John
<John.Stanbrook@whrsd.k12.ma.us>; Mike Carroll <mike.carroll@collierseng.com>; Troy Randall <randall@ai3architects.com>; Julie Rivera
<rivera@ai3architects.com>; Mike Reith <mike.reith@collierseng.com>; Katie Cronin <Katie.Cronin@MassSchoolBuildings.org>; Matt Donovan
<Matt.Donovan@MassSchoolBuildings.org>; Christina Forde <Christina.Forde@MassSchoolBuildings.org>
Subject: MSBA/Whitman-Hanson Regional School District – Whitman Middle School Project, Scope and Budget Agreement
This Message originated outside your organization.